Current New Construction

Last Updated: January 23, 2017


River Mile   Structure % complete
162.3 R Weir 0
162.2 R Weir 0
162.1 R Weir 0
162.0 R Weir 0
161.7 L Dike 100
161.5 L Dike 100
161.1 L Dike 100
73.6 L Chevron 100
72.9 L Dike 100
72.5 L Chevron 100
69.15 R Weir 0
68.95 R Weir 0
68.75 R Weir 0
68.1 L Z-Dike 100
67.75 L Dike  0
67.7 L Z-Dike 35
67.5 L Z-Dike 0
67.3 L Degrade Dike 48
67.3 L Revetment 0
67.1 L Degrade Dike 0
34.2 L Weir 0
34.1 L Weir 0
32.5 L Weir 0
32.4 L Weir 0
32.3 L Weir 36
32.2 L Weir 90
31.6 R Dike 100
30.8 R Weir 90
30.7 R Weir 90
33.1 L South Levee Revetment 0
33.9 L North Levee Revetment 0
33.6 L Perched Scour Hole Revetment 0
34.0 L North Levee Toe Revetment 0
33.3 L Kicker Dike 0
33.9 L Construction Access Dredging 0
34.1 L Construction Access Haul Road 0
10.3 L Degrade Dike 0
10.1 L Remove Pile Dike 0
10.1 L Side Channel Enhancement Dike 0
7.9 L Degrade Dike 0
3.0 L Dike 35
3.0 L Revetment 100
2.6 R Weir 95
2.5 R Weir 95
2.3 R Weir 95
2.2 R Weir 95

Proposed New Construction

Last Updated: January 23, 2017


River Mile Structure
257.9 L Weir
257.2 L Dike Extension
256.7 L Dike Extension
256.7 L Trail Dike
254.7 R Dike 
254.2 L Weir
254.1 L Weir
254.0 L Weir